When provincial support to acquire a new middle school site was withdrawn, New Westminster Schools was directed to create additional student spaces on existing district-owned property. 

The Ministry of Infrastructure identified Lord Tweedsmuir Elementary as the target site due to its central location, favourable ground conditions, and large lot size. To address severe current and projected seat shortages, the district was instructed to submit a formal business case that significantly increases the number of students this site can accommodate. 

While a business case does not ensure funding for the project, it is the first of several steps towards building the school. 

This direction to use a district-owned site for the Tweedsmuir project was incorporated into the 2026 Long-Range Facilities Plan (LRFP) update, which included two redevelopment options (“Scenario A” and “Scenario B”). Following public consultation, the Board of Education endorsed “Scenario A” on June 16, 2026. 

Business case “Scenario A”

“Scenario A” is a pathway towards a second secondary school in our community. The Lord Tweedsmuir campus will initially accommodate Grades 6-7 in the initial years, before transitioning to Grade 8-12 as our learning community continues to grow. 

This scenario will: 

  • See the adoption of a new district-wide grade reconfiguration to a K-7 and 8-12 grade model.  
  • Elementary Schools: Kindergarten to Grade 7.  
  • Secondary Schools: Grade 8 to Grade 12. 
  • Result in the conversion of our middle schools into elementary schools.   

If supported and funded by the Province, “Scenario A” addresses New Westminster Schools’ most pressing capacity challenge by creating a new secondary school in the district without first acquiring additional land. This is significant in New Westminster, where opportunities to purchase appropriately sized school sites are extremely limited.

Business case “Scenario C”

Following community consultation and the Board of Education’s endorsement of “Scenario A”, the Ministry gave district administration additional direction to explore a new potential outcome (“Scenario C”) and to remove “Scenario B” from consideration in the business case. 

Under “Scenario C”, the Tweedsmuir site would house a Kindergarten to Grade 12 campus, serving approximately 2,200 students. Due to the timing of this direction, we were unable to consult with our community. 

The District is investigating the feasibility of scenarios “A” and “C” in the business case and will submit both to the Province for funding consideration.

Stride Elementary

If the Tweedsmuir project is approved, the Ministry of Infrastructure has proposed temporarily relocating the Lord Tweedsmuir population to Burnaby’s former Stride Elementary School for the duration of construction. 

Relocation would provide a contractor with unrestricted access to the entire Tweedsmuir site. This may potentially simplify the new campus’ construction process. However, Tweedsmuir students will have to attend school outside of New Westminster until the project is complete, which will require daily transportation to Burnaby. 

We have also heard concerns from our community about relocating students out of our district, and the temporary use of a building that has not yet been replaced by the Provincial Government’s seismic mitigation program. Conversations with the Province are ongoing. 

Key projects and timeline

  • April 2026 – Ministry direction to proceed to business case for Lord Tweedsmuir site intensification and redevelopment. 
  • May 2026 – District communication and info session to the Lord Tweedsmuir learning community. 
  • June 2026 – Board endorsement of Scenario A of Long Range Facilities Plan for up to a  2,300 seat Junior-Secondary school (Grades 6 – 12). 
  • July 2027 – Direction received from the Ministry of exploring through our business case a Kindergarten to Grade 12 campus of up to 2,200 students. 
  • Fall 2026 – Anticipated submission of business case of Lord Tweedsmuir. 
  • TBD – Approval and funding of the Lord Tweedsmuir redevelopment. 

Questions and Answers

General questions

1. What is the cost of the project? Where is the funding coming from?

2. What is the district’s role in this project? What is the Provincial Government’s role?

3. Why can’t we keep students at the Tweedsmuir site while construction is taking place?

4. What will the catchment be like for the new school?

5. What configuration will the new school be and what programs will it host?

6. Why was the Lord Tweedsmuir site selected for this project?

7. How will the project affect properties close the site?

8. What analysis has been done regarding the traffic impact of expanding to two schools at the Lord Tweedsmuir site?

9. What do the plans for the two schools look like?

Stride Elementary questions

10. What is the status of the Stride Avenue school we will be moving into?

11. What is the capacity of Stride? Does Stride have capacity for the French students?

12. Will the students from both Tweeds and Stride be sharing the same greenspace and playground?

13. How will this move affect both private and District-operated daycares at Tweeds?

14. Will Tweedsmuir Teachers and Staff be moved together to the temporary location and then to the new school(s)?

15. Is there a bus stop for those using the accessibility bus at Stride?

16. Will there be a PAC at the Stride Avenue school?

17. What is library space like at Stride?

18. Will there be teacher parking at Stride?